• This is an assessment test.
  • To draw maximum benefit, study the concepts for the topic concerned.
  • Kindly take the tests in this series with a pre-defined schedule.

Arithmetic: Time and Work Test-5

Congratulations - you have completed Arithmetic: Time and Work Test-5.You scored %%SCORE%% out of %%TOTAL%%.You correct answer percentage: %%PERCENTAGE%% .Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1
If it takes A four days to dig a certain ditch, whereas B can dig it in 8 days and A, B, C together can dig it in $ \displaystyle 2\frac{2}{7}$ days, how long C alone would take to dig it?
A
8
B
4
C
6
D
16
Question 1 Explanation: 
Let the ditch take 16 units to dig up.
A does 4 units per day and B does 2 units per day.
A+B+C can do $ \displaystyle \frac{16}{\frac{16}{7}}=7\,units/day$
C does 7-4-2 = 1 unit of work per day.
Therefore, C digs the ditch in 16/1 = 16 days.
Question 2
A sum of Rs.25 was paid for a work which A can do in 32 days, B in 20 days, Band C in 12 days and D in 24 days. How much did C receive if all the four work together?
A
Rs.15/3
B
Rs.14/3
C
Rs.13/3
D
Rs.16/3
Question 2 Explanation: 
Let the total work be 480 units.Capture98
$ \displaystyle C'\,share\,=\frac{16}{15+24+16+20}=\frac{16}{75}\,\,of\,Rs.25=Rs.\,\frac{16}{3}$
Question 3
A cistern can be filled by two pipes filling separately in 12 and 16 min respectively. Both pipes are opened together for a certain time but being clogged, only 7/8 of full quantity water flows through the former and only 5/6 through the latter pipe. The obstructions, however, being suddenly removed, the cistern is filled in 3 min from that moment. How long was it before the full flow began?
A
4.5 min
B
2.5 min
C
3.5 min
D
5.5 min
Question 3 Explanation: 
Let the total quantity be 96p liters.
A fills @ 8p l/min. and B fills 6p l/min.
Rate of A+B /min= 8p + 6p = 14p l/min.
Now due to obstruction,
A’s rate is 8p X 7/8 = 7p l/min. and B’s rate is 6p x 5/6 = 5p l/min.
Total rate of A+B /min = 7+6 = 12p l/min.
Let the time for which the clog is there be t mins.
For 3 mins the pipes had a combined rate of 14p l/min.
In 3 mins pipes filled up = 14p x 3= 42p l/min.
Left (96 - 42)p l/min= 54p l/min.
Time when clogged pipes supplied the water is = 54p/12p = 4.5 mins.
Question 4
The work done by a woman in 8 h is equal to the work done by a man in 6 h and by a boy in 12 h. If working 6 h per day 9 men can complete a work in 6 days, then in how many days can 12 men, 12 women and 12 boys together finish the same working 8 h per day?
A
$ \displaystyle 2\frac{1}{2}$
B
$ \displaystyle 1\frac{1}{2}$
C
$ \displaystyle 3\frac{1}{2}$
D
None of these
Question 4 Explanation: 
Let the work be of 72 units.
1 woman does 72/8=9 units of work per hour.
1 man does 72/6=12 units of work per hour.
1 child can do 72/12=6 units of work /hour.
At 6 hours per day 9 men can do 9 x 6 x 12 units of work in 1 day.
Therefore, at  6 hours per day 9 men can do 9 x 6 x 6 x 12 units of work in 6 day.
12  men +12 women +12 children can do 12 (9+12+6) = 12 x 27 units of work in 1 hour 1 day.
Total number of hours required $ \frac{9\times 6\times 6\times 12}{12\times 27}=12\,\,hours$ The group can work for 8 hours per day.
Therefore it will take 12/8 = 1 ½ days to finish the work.
Once you are finished, click the button below. Any items you have not completed will be marked incorrect. Get Results
There are 4 questions to complete.
List
Return
Shaded items are complete.
1234End
Return

Want to explore more Arithmetic Tests?

Explore Our Arithmetic Tests

FREE CHEAT SHEET

Learn
How to Master VA-RC 

This free (and highly detailed) cheat sheet will give you strategies to help you grow

No thanks, I don't want it.

Join Our Newsletter

Get the latest updates from our side, including offers and free live updates, on email.

Rsz Undraw Envelope N8lc Smal
Rsz 1rsz Close Img