Arithmetic: Time and Work Test-6

Congratulations - you have completed Arithmetic: Time and Work Test-6.You scored %%SCORE%% out of %%TOTAL%%.You correct answer percentage: %%PERCENTAGE%% .Your performance has been rated as %%RATING%%
Your answers are highlighted below.
Question 1
8 men can complete a piece of work.in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work?
A
16 days
B
12 days
C
14 days
D
10 days
Question 1 Explanation: 
Let the amount of work be 320 units.
8 men do 1280 units of work in 20 days.
1 man can do 160 units of work in 20 days.
Therefore, 1 man can of 8 units of work per day.
Similarly, 1 woman can do {1280/(32 x 5)} = 5 units of work per day.
Therefore 5 men+ 8 women can do {(5 x 8) + (8X5)} = 80 units of work per day.
The number of days required to complete the work is$ \frac{1280}{80}=16days$
Question 2
M and N can do a work in 10 days and 15 days respectively. If M starts on the work and both work alternately day after day, in how many days will the work be completed?
A
10
B
12
C
8
D
9
Question 2 Explanation: 
Let the total work be = 30 units.
M does work at 30/10 = 3 units/day.
N does work at 30/15 = 2 units/day.
If they work alternatively, the total work finished in 2 days is 3+2= 5 units.
They can finish the work in 30/5 = 6 days working in pairs .
Total days required = 6 x 2 = 12 days.
Question 3
3 men can complete a piece of work in 6 days. 5 women can complete the same work in 18 days. In how many days will 4 men and 10womentogether complete the same work?
A
3 days
B
5 days
C
2 days
D
days
Question 3 Explanation: 
Let the work be 180 units.
3 men do 180 units in 6 days.
1 man can do 180/(6 x 3) = 10 units in 1 day.
4 men in 1 day do 40 units of work.
5 women can complete 180 units of work  in 18 days.
In 1 day 1 woman does  {180/(18 x 5)} = 2 units of work.
10 women in 1 day do 20 units of work.
Total per day = 40+20 = 60 units of work.
The work can be finished in 180 /60 = 3 days.
Question 4
A and B can finish a job in 10 days while Band C can do it in 18 days. A started the job worked for 5 days, then B worked for 10 days and the remaining job was finished by C in 15 days. In how many days could C alone have finished the whole job?
A
30 days
B
15 days
C
45 days
D
24 days
Question 4 Explanation: 
Capture9990
15C+10(10-C)+5(8+C) = 180,
=> 15C+100-10C+40+5C = 180
=> 10 C = 40
=> C= 4 units per day.
C can finish the work in 180/4 =45 days.
Question 5
Aman's basic pay for a 40 hours week is Rs.200. Overtime is paid at 25% above the basic rate. In a certain week, he worked overtime and his total was Rs.300. He therefore, worked for a total of (in hours):
A
52
B
56
C
58
D
62
Question 5 Explanation: 
For normal work he received 200/40 = Rs. 5 per hour.
If he received 25 % more then he receives = 5 x 5/4 = Rs. 6.25 per hour.
He received a total of 300.
Let him work on extra wage for x days.
Therefore, 200 + 6.25x= 300,
x= {(100 x 4)/(5 x 5)}= 16 days.
Aman worked for total 40+16 = 56 days.
Once you are finished, click the button below. Any items you have not completed will be marked incorrect. Get Results
There are 5 questions to complete.
List
Return
Shaded items are complete.
12345
End
Return

Want to explore more Arithmetic Tests?

Explore Our Arithmetic Tests

FREE CHEAT SHEET

Learn
How to Master VA-RC 

This free (and highly detailed) cheat sheet will give you strategies to help you grow

No thanks, I don't want it.

Join our Free TELEGRAM GROUP for exclusive content and updates

Rsz 1rsz Close Img

Join Our Newsletter

Get the latest updates from our side, including offers and free live updates, on email.

Rsz Undraw Envelope N8lc Smal
Rsz 1rsz Close Img